Road Closure Schedule for Richmond Village
Below is a coordinated road closure plan related to concurrent infrastructure projects with multiple municipal partners that will affect the east end of the village of Richmond:
Phase 1
(Mon, Sept 24th @ 7:00am - Fri, Sept 27th @ 6:00pm)
Closure of Barnsdale Road while work on the Forcemain continues on Eagleson Road (Northbound lane).
Phase 2
(Fri, Sept 27th @ 6:00pm - Mon, Sept 30th @ 6:00am)
Forcemain project opens Eagleson Road Northbound. Barnsdale Road opens for the weekend and the Forcemain project closes Old Richmond Road for the weekend only.
Phase 3
(Mon, Sept 30 @ 6:00am - Sun, Oct 06 @ 6:00pm)
Forcemain project will reopen Old Richmond Road while Barnsdale Road is closed again.
Forcemain project will fully close Eagleson Road south of Richmond (from Old Richmond Road to Ottawa Street).
Phase 4
Forcemain project will reopen Eagleson Road fully on Sunday, Oct 06th at 6:00pm.
Hydro continues work on Barnsdale Road until Friday, October 11th at 6:00pm.