Road Closure Schedule for Richmond Village

Below is a coordinated road closure plan related to concurrent infrastructure projects with multiple municipal partners that will affect the east end of the village of Richmond:


Phase 1
(Mon, Sept 24th @ 7:00am - Fri, Sept 27th @ 6:00pm)

  • Closure of Barnsdale Road while work on the Forcemain continues on Eagleson Road (Northbound lane).


Phase 2
(Fri, Sept 27th @ 6:00pm - Mon, Sept 30th @ 6:00am)

  • Forcemain project opens Eagleson Road Northbound. Barnsdale Road opens for the weekend and the Forcemain project closes Old Richmond Road for the weekend only.


Phase 3
(Mon, Sept 30 @ 6:00am - Sun, Oct 06 @ 6:00pm)

  • Forcemain project will reopen Old Richmond Road while Barnsdale Road is closed again.

  • Forcemain project will fully close Eagleson Road south of Richmond (from Old Richmond Road to Ottawa Street).


Phase 4

  • Forcemain project will reopen Eagleson Road fully on Sunday, Oct 06th at 6:00pm.

  • Hydro continues work on Barnsdale Road until Friday, October 11th at 6:00pm.