Construction Update: Richmond Forcemain Twinning Project (Phase 2)

Sanitary forcemain twinning work in the Village of Richmond is ongoing and the construction will involve a weekend intersection closure at the end of September immediately followed by a seven-day road closure leading into early October. Signed detours will be in place for the duration of the closures.  

Scope of Work

The proposed works include crossing of the new sanitary sewer forcemain on Eagleson Road towards the Jock River.

The work is being completed to improve the reliability and operations of the existing Village of Richmond wastewater pumping station and extend the lifespan of the existing forcemain and to replace culverts at the end of their service life.

During the road closures, residents along Eagleson Road can expect to be detoured to the north to Fallowfield Road or to the south to Brophy Drive. The detours will be coordinated with the concurrent Hydro Ottawa closure of Barnsdale Road.

Eagleson Road northbound will be open to traffic prior to either of these road closures being implemented.

More details can be found below or by visiting the City’s website here.

Timing of Work

6:00pm on Friday, September 27th to 6:00am on Monday, September 30, 2024

  • Old Richmond Road between Fallowfield Road and Eagleson Road will be closed and the intersection of Eagleson Road and Old Richmond Road will be partially closed.

  • A signed detour using Eagleson Road and Fallowfield Road will be in place for the duration of the closure. 

6:00am on Monday, September 30th to 6:00pm on Sunday, October 6, 2024

  • Eagleson Road will be closed between Old Richmond Road and Barnsdale Road.

  • A signed detour using Old Richmond Road, Moodie Drive, Ottawa Street and Brophy Drive will be in place for the duration of the closure.

Location of Work

The road closures will be along Old Richmond Road between Fallowfield Road and Eagleson Road, and along Eagleson Road between Old Richmond Road and Brophy Drive.