🚧Construction Updates🚧

Current Projects

Road Resurfacing & Construction Impacts
A number of resurfacing, maintenance, and preservation projects are scheduled across Ward 21 in the coming months. Some work will include nighttime construction between 10:00 p.m. and 7:00 a.m., which may result in temporary noise impacts for nearby residents.

We will continue to share updates as these projects progress and appreciate your patience during this work to improve our roads.

🛣 Resurfacing Projects

  • Bankfield Road
    From 320m east of Hwy 416 overpass to Kilreen Lane
    Start: Late July (work to tentatively start week of July 21) – Early September

  • Moodie Drive
    From Fallowfield Road to 1300m north
    Start: Early July (work to tentatively start first week of July) - Late September

  • Twin Elm Road
    From Brophy Road to 3890m north
    Start: Late July (work to tentatively start week of July 28) - Late September

  • Brophy Road
    From 25m east of Fourth Line Road to 326m west of Hwy 416 overpass
    Start: Late July (work to tentatively start week of July 21) - Late September

  • Eagleson Road
    From Old Richmond Road to Fallowfield Road
    Status: Work ongoing until end of summer (*Road closure will commence on July 2nd*)

  • Third Line Road
    From Phelan Road W to Prince of Wales Drive
    Start: Early September (tentative start date of September 8)

  • Third Line Road
    From 115m south of Prince of Wales Drive to Roger Stevens Drive
    Start: Late August (tentative start date of August 27)

🔧 Crack Sealing (Starting September)

  • Flewellyn Road – From Ashton Station Road to Munster Road (tentative start date of September 26)

  • Ashton Station Road – From Ormrod Road to Flewellyn Road (tentative start date of September 8)

  • Ormrod Road – From Ashton Station Road to Flewellyn Road (tentative start date of September 9)

🚜 Gravel Road Upgrades

  • Phelan Road West
    From Prince of Wales Drive to Ormond Road
    Status: Work ongoing

🛡 Pavement Preservation

  • Conley Road
    From Franktown Road to Mansfield Road
    Start: Mid-July


🌉 Culvert Renewals

As part of a major infrastructure renewal project, the City of Ottawa will be replacing seven culverts across Ward 21 over the coming months. These upgrades are critical for maintaining safe and reliable roadways, particularly in areas prone to flooding or seasonal runoff.

Construction will take place at the following locations:

🛠 Scheduled Culvert Replacements

  • William McEwen Drive
    0.01 km north of Brophy Drive
    📅 July 14–18

  • Brophy Drive
    0.43 km east of Eagleson Road
    📅 July 21–25

  • Brophy Drive
    0.58 km west of Fourth Line Road
    📅 July 21–25

  • Third Line Road
    0.01 km south of Brophy Drive
    📅 July 28 – August 1

  • Second Line Road
    0.10 km north of Roger Stevens Drive
    📅 Planned for Fall 2025

🚧 Traffic impacts and detours may be in place during these dates. Please follow posted signage and allow extra travel time when passing through these areas.


🚧 Other Construction Projects

➔ Richmond Roundabout – Final Minor Work
Cavanagh Construction crews will be completing final touch-ups on the Richmond roundabout on Wednesday, July 2 and Thursday, July 3, between 9:00 AM and 3:30 PM.
 
Scheduled Work:

  • Granular placement for shouldering

  • Granular placement along the handrail

  • Rip rap placement at the BMR entrance

  • Miscellaneous debris cleanup

  • Sod replacement

  • Settled paver and tile relay

Traffic Impact:

  • Rip rap and granular work will be completed with the help of flaggers positioned outside of the roundabout.

  • Sod and paver work will occur behind the curb and is expected to cause minimal disruption to traffic.

Thank you for your patience as this work wraps up and the roundabout is finalized for long-term use.

➔ Upcoming Hydro Work on Dwyer Hill Road
Starting July 7, 2025, Hydro Ottawa will begin installing new hydro poles and equipment along Dwyer Hill Road, between Franktown Road and Jock Trail Road. 

Project Details:

  • Contractor: Bradley Kelly Construction Ltd.

  • Estimated Completion: September 26, 2025

  • Impacted Streets: Ashton Station Road, Dwyer Hill Road, and Purdy Road

  • Affected Customers: 49

Affected customers will receive written notices delivered to their door with details about the upgrade. If planned power outages are required for safety, additional notices will be issued in advance to notify impacted households.

🗺 To explore citywide construction projects, use the City of Ottawa Interactive Construction Map.

Next
Next

Newsletter - 26 June 2025